Can the use of temporary nose in incremental launching method reduce the cantilever moment of superstructure to the value of inner support moment?


Temporary nose used to reduce the cantilever moment, that arises from the nature of incremental launching of the superstructure, the temporary nose will be attached to the superstructure front temporary nose and the length of the temporary nose usually is 0.60-0.65 of bridge span length, central prestressing used in conjunction with temporary nose to reduce tensile stresses on concrete during the launching.

Figure 1









The bending moment due to self-weight of the long bridge with equal spans at piers=-0.0883WL^2 and bending moment at the mid-span equal 0.0417WL^2. where W is the unit weight of superstructure and L is the length of spa), without using temporary nose the bending moment at the lead pier could reach to a value of -0.5WL^2, theoretically the cantilever bending moment can be reduced to internal support bending moment by using very long temporary nose, the using of this huge nose will not be economical and practical at fields, therefore we use temporary nose with central prestressing to reduce the tensile stresses on structure to acceptable value.




Comments

Videos from My Youtube channel

Popular posts from this blog

Binding wire for steel reinforcement

stress-strain diagram for aluminium alloy and rubber

Concrete repair-selecting the repair method

Rebar Splicing and Overlapping — ACI 318-19 Requirements Explained

Pile cap

Prestressing strand manufacturing

Non-Working Pile Testing and Static Compression Load Test

The reasons behind the trimming of pile head

Fiber Reinforced polymer for strengthening of reinforced concrete

Nominal maximum size of coarse aggregate