How to check the rate of applying of prime coat at site

Prior to laying asphalt, we usually spray prime coat above the aggregate road base to seal the last layer of aggregate, and to prevent moisture from damaging the laid of asphalt. the prime coat should be sprayed at a specific rate. The rate of spraying the prime coat can vary as per the project specifications. The rate of applying prime coat can range from 0.6 Kg/m2 to 1Kg/m2 and it can vary from different countires.  



Figure 1

Verifying the rate of application will be simply done by placing a square piece of plywood or filler board. We will measure the weight of the filler board weight before applying the prime coat and after applying the prime coat. The rate of application will be the difference in weight divided by the area of the filler board. Figure no:02 show a filler board placed during the spraying of the prime coat to measure the rate of application.

Figure 2




Comments

Videos from My Youtube channel

Popular posts from this blog

Rebar Splicing and Overlapping — ACI 318-19 Requirements Explained

Binding wire for steel reinforcement

Pile cap

Repairing of concrete bulging

why do we stagger reinforcement overlapping?

Bridge Diaphragm

Example 1:Flexural stress calculation using transformed area method for rectangular beam with double layer of reinforcing bars

Non-Working Pile Testing and Static Compression Load Test

Prestressing stands debonding

stress-strain diagram for aluminium alloy and rubber