nominated subcontractor

the nominated subcontractor is a subcontractor who stated in contracts or whom the engineer instruct the contractor to employ under clause 13.






the contractor has the right to object the nomination. the contractor shall notify the engineer of his objection providing supporting evidence. the objection shall be deemed reasonable if the objection arises from following

  1. The nominated subcontractor has insufficient competence, resources or finance strength.
  2. if the subcontract doesn't specify that the nominated subcontractor shall indemnify the contractor for any damage such as misuse of goods or any kind of negligence caused by a nominated subcontractor or his agents.
  3.  if the subcontract doesn't specify for the subcontracted work that nominated subcontractor shall     
  • be liable and obligated for subcontracted work. therefore the contractor will be able to discharge his obligation and liabilities under the contract
  •   indemnify the contractor against any obligation or liabilities arising from contract and any failure to perform obligations and liabilities   
the objection can be rejected if the engineer accepted to indemnify the contractor against and from any consequences arises from previous points     

payment for nominated subcontractor shall be done by the contractor. the contractor shall pay the nominated subcontractor the amount certified by the engineer. the engineer may ask the contractor to provide evidence of paying the nominated subcontractor for previous payment certificates.
if the contractor didn't pay the subcontractor then the employer may pay the nominated subcontractor directly for all pending certified amounts. then the contractor should repay the employer all the paid amounts.






      

Comments

Popular posts from this blog

Bar Bending schedule (BBS)

Binding wire for steel reinforcement

Pile cap

Repairing of concrete bulging

stress-strain diagram for aluminium alloy and rubber

Non-working piles

Bridge Diaphragm

Nominal maximum size of coarse aggregate

shear key

The reasons behind the trimming of pile head

My photo
Mohammad
My name is Mohammad Hamdan, and I am a Civil/bridge Engineer with extensive professional background and experience in the field of construction. I have 10+ years of experience in the construction field. During my professional career, my emphasis has been placed on structural projects, mainly bridges, infrastructure and roads. Reading and practicing the design of structures is my passion.i was lucky to be a part of a big team that executed major highway interchanges. I believe in spreading the knowledge, thus, i compose these courses to share my experience and knowledge. My course focuses on the practical side of construction field. On other word, i am sharing some of what new engineers need to know about construction field. Beside working on construction field, i love writing some articles on my website ( curious civil engineer) Moreover, i wrote some engineering papers, you can check them  by searching my name on Google (Mohammad mamon Hamdan)