Video from my YouTube channel

Subscribe to My You tube channel

Pile heave



Driving piles will cause soil displacement. As a result, the previously driven pile will move upward and laterally. Pile heave value directly proportional to soil displacement. Therefore, as the number of driven piles increased pile heave will increase. The heave in cohesive soil is significant. As a result, the heave should be considered in the design stage. Using low displacement piles and improved method of installation (such as predrilling to reduce soil displacement) may consider if the calculated heave values are enormous.

In the events of adjacent piles heave while driving new piles more than 13 mm for end bearing piles. Pile shall be re-driven. Similarly, adjacent piles shall be re-driven if the upward movement is more than 38 mm for friction piles.


Figure 2

Comments

Videos from My Youtube channel

Popular posts from this blog

Pile cap

Bridge Diaphragm

Prestressing stands debonding

Binding wire for steel reinforcement

Fiber Reinforced polymer for strengthening of reinforced concrete

Concrete repair-selecting the repair method

stress-strain diagram for aluminium alloy and rubber

Non-Working Pile Testing and Static Compression Load Test

Example 1:Flexural stress calculation using transformed area method for rectangular beam with double layer of reinforcing bars

Prestressing strand manufacturing